The process of forming a
City Improvement District (CID) The
process of forming a CID is governed by the Gauteng City Improvement Districts Act of
1997. The Act requires certain information to be compiled and submitted in the form of a
petition to the City Council. It is a participative process and therefore a number of
public meetings must be held. May: The first
meeting will take place on Thursday 15 May at 18:00
at Ongoing: draft versions of the business plan August: A second
meeting will be held in August if needed. September: By
registered mail, all property owners will be sent the summary of the business plan and a
voting form. October: Create
levy schedule analysis. Public meeting to declare the area a CID, finalise the business
plan and levies. November: Submit
all documentation to the City Council Subsequently
(approx 3-4 months): All
property owners notified of the City Councils final decision by registered mail.
Assuming favourable outcome, establishment of a Section 21 company.
|
|